Wastewater System Improvements

Published by
This project entailed the installation of 8,000 feet of 24-inch SDR35 sewer pipe, along with the placement of 50 manholes. A significant segment of the project, spanning 300 feet, required a depth of 24 feet and was located on Monument Lake Road. To manage the sewage flow during the entire duration of the project, a pump-around system was utilized, employing four 4-inch pumps.